• InfoDrainage
  • Civil 3D

Completing the hydraulic design in InfoDrainage

Configure the stormwater design options for subcatchments and complete the hydraulic design in InfoDrainage.


Tutorial resources

These downloadable resources will be used to complete this tutorial:

ifdr2023_M12_data.zip

Step-by-step

InfoDrainage is very powerful in its ability to calculate the appropriate sizes and types of stormwater drainage system elements for you. This is why, once you have successfully imported a CAD file that was started in Civil 3D, you can complete the hydraulic design in InfoDrainage.

  1. Review the data for the first catchment. Place your cursor over the catchment icon and click to open its properties.

To change the percentage impervious value for all the catchments in the model and set the Preliminary Percentage Impervious value to 60:

  1. In the Catchment – (1) dialog box, Runoff tab, set Percentage Impervious to 60.
  2. Set Time of Concentration to 5 minutes.
  3. Set the Volumetric Runoff Coefficient to 0.75.
  4. Click OK.

The Plan View in InfoDrainage with a model imported. A catchment icon is highlighted and the dialog box displaying the catchment’s properties is open. The options in the dialog box are configured.

  1. On the ribbon, Build tab, Data panel, click Tables.

The InfoDrainage ribbon, Build tab, Data panel with the Tables command selected.

  1. In the Tables dialog box, select the Inflows tool.

The Tables dialog box with the Inflows tool called out with a large arrow.

  1. In the left pane, expand the Inflows node.
  2. Expand the Catchment Area node.
  3. Enable Preliminary Percentage Impervious, Preliminary Volumetric Runoff Coefficient, and Volumetric Runoff Coefficient.
  4. Expand Time of Concentration and enable Percentage Impervious.
  5. In the Percentage Impervious column, select the first cell, then click and drag to select all the cells.
  6. In the toolbar, enter 60 into the box.
  7. Click the equals sign (=).

To set the Volumetric Runoff Coefficient:

  1. Select all the cells under the Volumetric Runoff Coefficient.
  2. Repeat steps 13 and 14 to change those values to 0.75.

Note: the Area values have all been calculated for you.

  1. Click OK.

The Tables dialog box. In the tree list, Inflows is selected, the appropriate catchment areas are selected, and the appropriate times of concentration are also selected. In the table, the Preliminary Percentage Impervious has been set as well as the Volumetric Runoff Coefficient.

To configure the analysis:

  1. On the ribbon, Analysis tab, Criteria panel, click Analysis Criteria.

The ribbon, Analysis tab, Criteria panel, with Analysis Criteria command selected.

  1. In the Analysis Criteria dialog box, select both the All and FSR rainfall studies, and then click OK.

The Analysis Criteria dialog box with All and FSR rainfall types selected.

To set up the preliminary sizing for the pipes:

  1. On the ribbon, Preliminary Sizing tab, Network Design panel, click Network Design Criteria.

The ribbon, Preliminary Sizing tab, Network Design panel, with the Network Design Criteria command selected.

  1. In the Network Design Criteria dialog box, Flow Options tab, expand the drop-down and select FSR.

The Network Design Criteria dialog box, Flow Options tab, with FSR selected.

  1. Click the Design Options tab.
  2. Accept the defaults and click OK.

The Network Design Criteria dialog box, Design Options dialog box, with default settings selected.

  1. On the ribbon, Preliminary Sizing tab, Network Design panel, open the Network Design Wizard.
  2.  On the Select Flow Path page, select which pipes you want to design.
  3. Click Next.

Network Design Wizard with the Flow Path pipes selected.

  1. On the Enter Flow Criteria page, accept the defaults for the rainfall and click Next.
  2. On the Enter Design Options page, accept the default options for the flow path and its network and click Next.
  3. On the Summary of Changes page, review the changes made during the network design.
  4. Click Finish.

The Network Design Wizard Summary of Changes page.

  1. Review the summary in the Network Design Report dialog box.
  2. Review the pipe profile and the changes to the flow path.
  3. In the Tree View, click Flow Path.
  4. Right-click Flow Path and select Show Profile.

Note: In the Profile – Flow Path dialog box, there is a different gradient, and the pipes are different sizes, both of which indicate the system has now been hydraulically designed.

The Profile – Flow Path dialog box with a gradient and different pipe sizes.

  1. To see the system data in greater detail, on the ribbon, Build tab, Data panel, click Tables.
  2. To see the pipe data, click the Connections tab.
  3. Review the table that populates with the new pipe data. Notice the Diameter / Base Width column contains the new pipe sizes.
  4. Click OK.

The Tables dialog box, Connections tab with data on the pipes.

  1. Save the network as Hydraulic Design

This InfoDrainage network can now be imported back into Civil 3D to complete the design.