When working in InfoSurge Pro, it is necessary to complete a successful steady state analysis before attempting to run a surge analysis.

To run a steady state analysis:

  1. From the Model Explorer, click the Run Manager button.

In the ArcGIS interface with InfoWater Pro initialized, in the Model Explorer, the Run Manager button being selected and highlighted in red.

  1. In the Run Manager dialog box, Standard tab, next to the Time Setting field, click More ().

In the Run Manager dialog box, Standard tab, next to the Time Setting field, the More (…) button selected and called out.

  1. In the Simulation Time dialog box, enable Steady State.
  2. Click OK to close the dialog box.

The Simulation Time dialog box with the Steady State option enabled and highlighted in red, and OK selected.

  1. Back in the Run Manager, click the Run icon to perform the simulation.

Upon successful completion, the status indicator should be green.