Transcript
00:01
Knowing how to create a pier schedule, obviously, this one is basically going to be practice.
00:05
In this segment, I'd like to create a pier foundation schedule.
00:11
Jump into Revit.
00:14
I'm going to go back to my South elevation.
00:16
Now, I'm going to go to the View tab.
00:19
I'm going to go to Schedules.
00:21
I'm going to go to Schedules, Quantities.
00:25
Now, let's scroll down to Structural Foundations.
00:31
And for the name, let's call it Pier Foundation Schedule.
00:39
Let's click "OK".
00:44
Now, let's add some values.
00:45
I'm going to scroll down to Type Mark.
00:50
Select it, add it, and grab my Type.
00:56
I'm going add it.
00:57
Going to grab that CIP Concrete Volume, going to add that.
01:04
Let's find some piles. We can get pile information, which is really cool.
01:08
So, I'm going to scroll down to where it says Piles, going to go counts, longitudinal and traverse row.
01:19
I guess Pile Diameter, Pile Length.
01:26
Looks good.
01:29
Now, I'm going to go to my Sorting and Grouping tab.
01:33
I want to sort by type mark.
01:38
I want to make sure grand totals is turned on.
01:44
I want to go to my Formatting tab, grab CIP concrete volume.
01:50
I want to make sure we calculate totals.
01:57
Now let's go to our Field Format.
02:01
Uncheck "Use Project Settings".
02:05
Let's select cubic yards.
02:09
Click "OK".
02:12
Click "OK" again.
02:15
Here we go.
02:16
Most important part is this right here.
02:18
Calculating our cubic yards.
02:20
Now we get an idea of where our footings are.
02:24
Grab F1.
02:25
Highlight your model.
02:27
Hit Close.
02:29
There we go.
02:31
Here, that's how you make a structural foundation schedule.
00:01
Knowing how to create a pier schedule, obviously, this one is basically going to be practice.
00:05
In this segment, I'd like to create a pier foundation schedule.
00:11
Jump into Revit.
00:14
I'm going to go back to my South elevation.
00:16
Now, I'm going to go to the View tab.
00:19
I'm going to go to Schedules.
00:21
I'm going to go to Schedules, Quantities.
00:25
Now, let's scroll down to Structural Foundations.
00:31
And for the name, let's call it Pier Foundation Schedule.
00:39
Let's click "OK".
00:44
Now, let's add some values.
00:45
I'm going to scroll down to Type Mark.
00:50
Select it, add it, and grab my Type.
00:56
I'm going add it.
00:57
Going to grab that CIP Concrete Volume, going to add that.
01:04
Let's find some piles. We can get pile information, which is really cool.
01:08
So, I'm going to scroll down to where it says Piles, going to go counts, longitudinal and traverse row.
01:19
I guess Pile Diameter, Pile Length.
01:26
Looks good.
01:29
Now, I'm going to go to my Sorting and Grouping tab.
01:33
I want to sort by type mark.
01:38
I want to make sure grand totals is turned on.
01:44
I want to go to my Formatting tab, grab CIP concrete volume.
01:50
I want to make sure we calculate totals.
01:57
Now let's go to our Field Format.
02:01
Uncheck "Use Project Settings".
02:05
Let's select cubic yards.
02:09
Click "OK".
02:12
Click "OK" again.
02:15
Here we go.
02:16
Most important part is this right here.
02:18
Calculating our cubic yards.
02:20
Now we get an idea of where our footings are.
02:24
Grab F1.
02:25
Highlight your model.
02:27
Hit Close.
02:29
There we go.
02:31
Here, that's how you make a structural foundation schedule.
Creating a Pier Foundation Schedule
Now that we can create a pier schedule, obviously this one is basically going to be practice! In this segment, I’d like to create a Structural foundation schedule.
- Open the model you have been working in
- You can be in any view to do this, but let’s go to the South elevation view anyway
- On the View tab, click Schedules then select Schedules Quantities
- Scroll down to Structural Foundations
- For the Name, type in PIER FOUNDATION SCHEDULE
- Click OK
- Select the parameters in the left column, click the Add button and add the parameters shown below, in this order:
- Go to the Sorting/Grouping tab
- Sort by: Type Mark
- Check Grand Totals on
- Go to the Formatting tab.
- Select CIP concrete volume
- Select Calculate totals:
- With CIP concrete volume still selected, click the Field Format… button.
- Uncheck Use project settings.
- Change the units to Cubic yards.
- Click OK
- Click OK again. You now have a schedule calculating your concrete volumes.