














Understand and create conceptual duct and pipe layouts.
Tutorial resources
These downloadable resources will be used to complete this tutorial:
Transcript
00:04
At the early stages of an mep project to create a
00:07
detailed mechanical layout can be time
00:10
consuming costly and most likely unnecessary
00:14
with duct and pipe sizes, fittings and detailed coordination.
00:18
Something to be considered at a later stage.
00:22
Single line, indicative mechanical layouts are more usual at this stage.
00:27
Moving to detailed design as the project progresses
00:32
in red,
00:32
this is taken care of by using duct and pipe placeholders,
00:37
duct and pipe placeholders carry the same intelligence as regular duct and pipe
00:41
but are represented by a single line and do not consider details such as fittings,
00:49
duct and pipe placeholders are found on the
00:51
rack panel and the plumbing and piping panel of the systems tab
00:56
ensure the current view is set to H VAC floor plans one mec.
01:03
In this view, the equipment has been placed only as a guide.
01:08
Let's start by creating a duct placeholder,
01:11
select duck placeholder from the ribbon.
01:13
And a review of the type selector shows that even though this is a placeholder,
01:18
the duck type can still be selected
01:21
and from the options bar, the size can be set,
01:24
giving you the option to make an early choice if required
01:28
changing the system type to supply air,
01:31
leave all other options as they are and draw
01:34
a duct run along the center of the corridor
01:36
at a nominal height of 9 ft.
01:39
Then at the riser,
01:41
change the elevation to zero and select apply from the options bar,
01:48
set the elevation back to 9 ft and draw branches to each of the phone
01:53
call units.
01:55
At the last two fan call units, draw a duct placeholder that crosses the main run
02:12
from the plumbing and piping panel. Select pipe placeholder
02:17
and changing the system type to chilled water flow.
02:20
Draw a run along the corridor below the supply duct run
02:24
again at a height of 9 ft.
02:27
Then at the riser change the elevation to zero
02:30
and select apply
02:37
follow the same procedure to create a pipe placeholder for chilled water return,
02:42
changing the elevation to zero at the riser.
02:49
Finally create branch pipes from the main run for chilled water flow and
02:54
for chilled water to return to each of the fan core unit positions
02:59
at a height of 9 ft.
03:05
Quick,
03:05
conceptual mechanical layouts can be created without the
03:09
need to consider final pipe and duct sizes
03:12
associated fittings, final elevations or detailed coordination.
03:20
Although it isn't necessary to set and change elevations while
03:24
creating an early stage layout using duct and pipe placeholders.
03:29
A view of this 3D model can indicate the intentions more clearly.
00:04
At the early stages of an mep project to create a
00:07
detailed mechanical layout can be time
00:10
consuming costly and most likely unnecessary
00:14
with duct and pipe sizes, fittings and detailed coordination.
00:18
Something to be considered at a later stage.
00:22
Single line, indicative mechanical layouts are more usual at this stage.
00:27
Moving to detailed design as the project progresses
00:32
in red,
00:32
this is taken care of by using duct and pipe placeholders,
00:37
duct and pipe placeholders carry the same intelligence as regular duct and pipe
00:41
but are represented by a single line and do not consider details such as fittings,
00:49
duct and pipe placeholders are found on the
00:51
rack panel and the plumbing and piping panel of the systems tab
00:56
ensure the current view is set to H VAC floor plans one mec.
01:03
In this view, the equipment has been placed only as a guide.
01:08
Let's start by creating a duct placeholder,
01:11
select duck placeholder from the ribbon.
01:13
And a review of the type selector shows that even though this is a placeholder,
01:18
the duck type can still be selected
01:21
and from the options bar, the size can be set,
01:24
giving you the option to make an early choice if required
01:28
changing the system type to supply air,
01:31
leave all other options as they are and draw
01:34
a duct run along the center of the corridor
01:36
at a nominal height of 9 ft.
01:39
Then at the riser,
01:41
change the elevation to zero and select apply from the options bar,
01:48
set the elevation back to 9 ft and draw branches to each of the phone
01:53
call units.
01:55
At the last two fan call units, draw a duct placeholder that crosses the main run
02:12
from the plumbing and piping panel. Select pipe placeholder
02:17
and changing the system type to chilled water flow.
02:20
Draw a run along the corridor below the supply duct run
02:24
again at a height of 9 ft.
02:27
Then at the riser change the elevation to zero
02:30
and select apply
02:37
follow the same procedure to create a pipe placeholder for chilled water return,
02:42
changing the elevation to zero at the riser.
02:49
Finally create branch pipes from the main run for chilled water flow and
02:54
for chilled water to return to each of the fan core unit positions
02:59
at a height of 9 ft.
03:05
Quick,
03:05
conceptual mechanical layouts can be created without the
03:09
need to consider final pipe and duct sizes
03:12
associated fittings, final elevations or detailed coordination.
03:20
Although it isn't necessary to set and change elevations while
03:24
creating an early stage layout using duct and pipe placeholders.
03:29
A view of this 3D model can indicate the intentions more clearly.