














Convert duct and pipe placeholder layouts.
Tutorial resources
These downloadable resources will be used to complete this tutorial:
Transcript
00:04
With traditional workflows.
00:06
Early stage mechanical layouts are sometimes discarded
00:10
as the project moves to detailed design
00:12
and the duct and piping networks recreated to
00:15
suit the requirements of the developing project.
00:19
Rivet duct and pipe placeholders can be used to leverage early stage
00:23
layouts to create detailed mechanical networks
00:26
utilizing and working with existing information.
00:29
Rather than starting over.
00:32
In this example,
00:33
we will review the duct and pipe placeholders already in the project,
00:37
then convert each layout to duct and pipe including fittings
00:41
while making positional changes as necessary.
00:44
We will finish by adding pipe accessories with the option of
00:47
additional duct and pipe accessories to complete the detailed layout.
00:53
Ensure the current view is set to H VAC floor plans.
00:58
One mec
01:01
let's start by reviewing the supply duct layout,
01:05
selecting a duct placeholder and reviewing the
01:08
properties shows the duct type size and elevation
01:13
using the tab key from the keyboard. Select the entire system
01:18
once selected use the type selector to change the duck type to round duct with Ts
01:25
and set the diameter to eight inches.
01:30
Finally select convert placeholder from the contextual ribbon tab.
01:38
The usual editing tools can now be used to make the necessary adjustments.
01:44
Remove the excess duct from the end of the system
01:50
and convert the cross fitting
01:52
to A T.
01:55
Then from the modify tab of the ribbon,
01:58
use the split element tool to create splits just after each takeoff along the run.
02:10
Select the first run of duct at the riser
02:14
and set the size to 14 inches.
02:23
Select the second run and set the size to 12 inches
02:34
and the third run to 10 inches.
02:41
Finally select a section of the main rum and
02:45
alter the elevation to 9 ft and four inches.
02:51
Further changes can be made to the duck type by selecting the relevant parts
02:56
of the network and choosing change type from the edit panel of the ribbon
03:00
and making the appropriate selection from the type selector.
03:06
Let's go ahead and convert the chilled water flow piping network in the same way,
03:14
use the tab key to chain,
03:16
select the pipework ensuring the pipework is
03:19
set to carbon steel screwed flange coupling.
03:24
Once selected, choose convert placeholder from the ribbon,
03:30
then remove the excess pipe at the end and convert the T to an elbow.
03:38
Finally
03:39
change the elevation for the piping network to 8 ft 10 inches
03:46
and the diameter to one and a quarter inches
03:56
follow the same procedure to convert the chilled water return piping network using
04:02
the same pipe type and setting the elevation to 9 ft nine inches.
04:12
Once converted, the piping networks can be repositioned
04:21
connected to equipment,
04:27
pipe and duct accessories can be added
04:34
and detailed coordination can be carried out,
04:39
finish connecting the remaining equipment to the
04:42
chilled water flow and chilled order,
04:44
return piping networks
04:46
and complete the detailed layout by adding pipe accessories.
04:51
If the details of the design are known at an early stage in a project,
04:55
then duct and pipe placeholders may not have been used
04:58
and a detailed coordinated layout created from the start.
05:02
However,
05:03
where placeholders have been used time can
05:05
be saved by utilizing the original intent
05:08
convert placeholders to duct and pipe
05:11
reposition and connect to equipment, fixtures and air terminals as required.
05:16
And finally add the appropriate duct and
05:19
pipe accessories to complete the detailed layout.
00:04
With traditional workflows.
00:06
Early stage mechanical layouts are sometimes discarded
00:10
as the project moves to detailed design
00:12
and the duct and piping networks recreated to
00:15
suit the requirements of the developing project.
00:19
Rivet duct and pipe placeholders can be used to leverage early stage
00:23
layouts to create detailed mechanical networks
00:26
utilizing and working with existing information.
00:29
Rather than starting over.
00:32
In this example,
00:33
we will review the duct and pipe placeholders already in the project,
00:37
then convert each layout to duct and pipe including fittings
00:41
while making positional changes as necessary.
00:44
We will finish by adding pipe accessories with the option of
00:47
additional duct and pipe accessories to complete the detailed layout.
00:53
Ensure the current view is set to H VAC floor plans.
00:58
One mec
01:01
let's start by reviewing the supply duct layout,
01:05
selecting a duct placeholder and reviewing the
01:08
properties shows the duct type size and elevation
01:13
using the tab key from the keyboard. Select the entire system
01:18
once selected use the type selector to change the duck type to round duct with Ts
01:25
and set the diameter to eight inches.
01:30
Finally select convert placeholder from the contextual ribbon tab.
01:38
The usual editing tools can now be used to make the necessary adjustments.
01:44
Remove the excess duct from the end of the system
01:50
and convert the cross fitting
01:52
to A T.
01:55
Then from the modify tab of the ribbon,
01:58
use the split element tool to create splits just after each takeoff along the run.
02:10
Select the first run of duct at the riser
02:14
and set the size to 14 inches.
02:23
Select the second run and set the size to 12 inches
02:34
and the third run to 10 inches.
02:41
Finally select a section of the main rum and
02:45
alter the elevation to 9 ft and four inches.
02:51
Further changes can be made to the duck type by selecting the relevant parts
02:56
of the network and choosing change type from the edit panel of the ribbon
03:00
and making the appropriate selection from the type selector.
03:06
Let's go ahead and convert the chilled water flow piping network in the same way,
03:14
use the tab key to chain,
03:16
select the pipework ensuring the pipework is
03:19
set to carbon steel screwed flange coupling.
03:24
Once selected, choose convert placeholder from the ribbon,
03:30
then remove the excess pipe at the end and convert the T to an elbow.
03:38
Finally
03:39
change the elevation for the piping network to 8 ft 10 inches
03:46
and the diameter to one and a quarter inches
03:56
follow the same procedure to convert the chilled water return piping network using
04:02
the same pipe type and setting the elevation to 9 ft nine inches.
04:12
Once converted, the piping networks can be repositioned
04:21
connected to equipment,
04:27
pipe and duct accessories can be added
04:34
and detailed coordination can be carried out,
04:39
finish connecting the remaining equipment to the
04:42
chilled water flow and chilled order,
04:44
return piping networks
04:46
and complete the detailed layout by adding pipe accessories.
04:51
If the details of the design are known at an early stage in a project,
04:55
then duct and pipe placeholders may not have been used
04:58
and a detailed coordinated layout created from the start.
05:02
However,
05:03
where placeholders have been used time can
05:05
be saved by utilizing the original intent
05:08
convert placeholders to duct and pipe
05:11
reposition and connect to equipment, fixtures and air terminals as required.
05:16
And finally add the appropriate duct and
05:19
pipe accessories to complete the detailed layout.